Good Morning!
Site work has continued on the Springport Rebuilding project on M-99 from South St to Gibbs Rd. Work began the end of March. Construction schedule has shifted due to utility delays, and some portions of the work will be moved into 2027. Lane closures will continue throughout the project. We will keep everyone as informed as possible with these updates.
Progress Report:
Water Meter Pits
Storm Sewer
Shoulder Widening
Sidewalk, Curb & Gutter, Driveways
New Signal
Upcoming Work:
Storm Sewer
Underdrain
Watermain
Paving