06/18/2026
🚧2024 Bond at Work 🚧
The Navarro South Elementary project has officially transitioned from foundational groundwork to vertical construction, and the school is truly beginning to take shape.
👷♀️The final foundation pour (for the gymnasium area) is complete! With the footprint finalized, steel er****on is now actively underway, bringing the building's frame into view.
🏗Vertical progress is moving fast inside the footprint, with crews currently building the structural masonry walls for the new kitchen area.
🚗The roadwork expansion is officially complete, helping improve future traffic flow. Crews are now shifting focus to pouring sidewalks and installing critical site drainage.
Every day brings visible changes to the site. Now that the steel structure is going up, the community will really be able to watch our new elementary school come to life from the road!