SEWER CONSTRUCTION UPDATE FOR WEEK ENDING 10/16/26
For the week starting Monday October 12th the RBO crew installed 100 feet of pipe and three stubs on Winslow Street. Crews are off Jerome Smith Road and will continue on Winslow Street now for the duration.
On Monday October 19th and Tuesday October 20th, the RBO crew will be working on Winslow Street right at the VMCC entrance. You will only be able to enter the parking lot from the Monument side of Winslow Street. There will be a police detail there to assist with traffic. For the rest of the week and continuing through the rest of October the RBO crew will be on Winslow Street installing stubs. This work will start at the VMCC end of Winslow Street and work towards Jerome Smith Road. Jerome Smith Road is open, but Winslow Street will still be closed during the day. Work will start at 7am and end at 4pm daily and will involve full road closures. You must plan ahead for parking as well as entering or exiting your property during working hours. For those of you who need to get to the school or the community center, please enter Winslow Street from Bradford Street. You will need to exit through the monument parking lot.
For the look ahead, once the RBO crew is done on Winslow Street they will move to Jerome Smith Road. That work will be between Winslow Street and Alden Street. We will have more updates on that in the following weeks.
The sewer team would like to thank you in advance for your cooperation and understanding during this very important project. If you have any questions or concerns, please call or email Sherry Prada, DPW Deputy Director at 508-487-7060 or [email protected].
Send a message to learn more