10/14/2026
Bond Project Update! We’re making incredible progress across our facilities.
Merritt Gym
-Hydration Ready: Drinking fountains are now installed and operational!
-Climate Control: The rooftop HVAC unit has been successfully placed.
-Court Ready: The new flooring is down, and the court paint is complete!
-Next Steps: Final cleaning is scheduled for October 16.
CTE Building
-Top Covered: Roof installation is 100% complete!
-Framing Up: Interior wall work is officially underway.
-Groundwork: Concrete grading is currently in progress.
-Coming Soon: Exterior siding will start going up very soon!
Thank you to our community for your continued support as we build better spaces for our students thanks to the passing of the 2024 Bond! Stay tuned for more progress updates.