Update on how the construction is progressing. Things are on schedule, budget is still in excellent shape with a little over $7.5 million in contingency.
They are getting close to having the building fully closed up, windows in, so things will be weathertight for the winter. Lots of interior work ongoing, drywall going in. It’s really starting to look like a school.
Look for a big update with more video and pictures first week of December. Building Committee, School Committee, and Board of Selectmen will all have an opportunity to tour the building so I’ll get a ton pictures and video from inside so everyone can see how things are progressing.
Hard to believe we’ll be welcoming students this coming August!