LeTourneau University Development

Call Directions Website Contact the school

LeTourneau University Development Generosity with purpose. Progress with faith. Partner with us in building The Christian Polytechnic University.

Progress—both above and below ground.Crews are making significant progress on the Christian Polytechnic University Cente...
10/07/2026

Progress—both above and below ground.

Crews are making significant progress on the Christian Polytechnic University Center (The Burks Center) on foundations and the first areas of slab-on-grade, while underground electrical, plumbing, stormwater, and utility work continues across the site. Column footers are now 75% complete, grade beams are 65% complete, and sanitary and storm sewer rough-ins are nearing completion.

More than 800 cubic yards of concrete have now been placed, and the next few weeks will bring continued foundation work, additional underground infrastructure, and crane mobilization—another sign that the project is preparing to move into its next visible phase.

Every foundation, utility line, and concrete pour is helping prepare a future space designed to serve LeTourneau students for generations.

Thank you to everyone helping us continue to Build with Purpose.

10/02/2026
Abbott Aviation Project UpdateThe hangar addition is beginning to rise!Structural beams are now going up at Abbott Aviat...
09/29/2026

Abbott Aviation Project Update

The hangar addition is beginning to rise!

Structural beams are now going up at Abbott Aviation, giving the new hangar addition its first real sense of vertical shape and scale. Nearby, foundation work continues as crews also move forward with electrical infrastructure and elevator shaft blocking for the expanding facility.

It’s an exciting stage of the project—moving from slabs and foundations to a structure you can begin to see taking form.
Each beam, conduit, and foundation element is another step toward expanded spaces where future LeTourneau aviation students will learn, train, and prepare for lives of purpose and service.

Thank you to everyone whose generosity continues to move this project forward.

09/26/2026
 Sometimes, a lasting relationship begins with one conversation.In 2010, Sidney Allen reflected on the first time LeTour...
09/25/2026



Sometimes, a lasting relationship begins with one conversation.

In 2010, Sidney Allen reflected on the first time LeTourneau caught his attention. At a Greggton Rotary Club meeting, LETU engineering student David Eaton gave a presentation about LEGS, a student project developing low-cost prosthetic legs for amputees in the developing world.

Sidney was intrigued enough to visit campus and see the students’ work for himself. What he saw led to his first gift to LeTourneau, supporting the LEGS program. From there, Sidney and his wife, Anna Lee, continued investing in the university, including support for the Belcher Center.

But their story didn’t stop there.

The Allens eventually established an endowed nursing scholarship, creating support designed to benefit LeTourneau students for generations. Sidney’s motivation was rooted in both student opportunity and the needs of the Longview community.

It’s a great reminder that generosity often begins by simply seeing the mission up close.

One student presentation. One campus visit. One first gift. And an impact that continues far beyond that moment.

That’s what building with purpose can look like.

At LeTourneau, learning has never been confined to a textbook.One of the priorities of the Build with Purpose campaign i...
09/23/2026

At LeTourneau, learning has never been confined to a textbook.

One of the priorities of the Build with Purpose campaign is to Deliver Premier Lab Experiences—creating and equipping spaces where students can move from theory to practice, test ideas, solve problems, and develop the skills they’ll carry into their professions.

From aviation and engineering to science, health sciences, and technology, hands-on learning is a defining part of the LeTourneau experience.

Projects taking shape across campus are helping strengthen that tradition and prepare the next generation of students to learn with both their minds and their hands.

There is still an opportunity to help equip the spaces where that learning happens.

Support Build with Purpose: https://www.letu.edu/development/build/priority-christian-identity.html

It's amazing to see the Christian Polytechnic University Center foundation taking shape, with plenty happening both abov...
09/22/2026

It's amazing to see the Christian Polytechnic University Center foundation taking shape, with plenty happening both above and below ground.

Crews are advancing earthwork and underground utilities, while electrical and plumbing rough-ins, elevator pits, and foundations continue. General grading is now 85% complete, and work is also progressing on stormwater lines, the west water line, column footers, the main electrical duct bank, and fiber conduit.

And a lot of dirt has been moved along the way: more than 14,600 cubic yards of earth have been hauled out, along with more than 1,500 tons of rock received and nearly 470 cubic yards of concrete placed to date.

Looking ahead, crews will continue work on concrete foundations, electrical and data duct banks, fire lanes, plumbing rough-ins, underground fire water, and sanitary sewer installation.

Each step is laying the groundwork for a space that will serve LeTourneau students for generations to come.

Thank you to everyone whose generosity is helping Build with Purpose. More updates to come.

 In the mid-1990s, LeTourneau was looking ahead.The Solheim Recreation and Activity Center was described as a cornerston...
09/18/2026



In the mid-1990s, LeTourneau was looking ahead.

The Solheim Recreation and Activity Center was described as a cornerstone project—one intended to expand service to students, strengthen outreach to the community, and help attract future generations of YellowJackets.

That vision was closely tied to John Solheim (MT ’64), LeTourneau’s 1995 Alumnus of the Year. In addition to his leadership at Karsten Manufacturing, John served on the University’s Board of Trustees and played an important role in the development and funding of the new Solheim Center. He also helped support LeTourneau Aviation through aircraft donations and encouraged alumni engagement in Phoenix.

What was once a rendering and a plan became a place that has served students for decades.

That’s one of the remarkable things about giving to LeTourneau: today’s investment can become tomorrow’s campus landmark, student experience, or opportunity. There’s more to come.
https://www.letu.edu/development/build/index.html

Then and now, we’re still Building with Purpose.

 In the mid-1990s, LeTourneau was looking ahead.The Solheim Recreation and Activity Center was described as a cornerston...
09/18/2026



In the mid-1990s, LeTourneau was looking ahead.

The Solheim Recreation and Activity Center was described as a cornerstone project—one intended to expand service to students, strengthen outreach to the community, and help attract future generations of YellowJackets.

That vision was closely tied to John Solheim (MT ’64), LeTourneau’s 1995 Alumnus of the Year. In addition to his leadership at Karsten Manufacturing, John served on the University’s Board of Trustees and played an important role in the development and funding of the new Solheim Center. He also helped support LeTourneau Aviation through aircraft donations and encouraged alumni engagement in Phoenix.

What was once a rendering and a plan became a place that has served students for decades.

That’s one of the remarkable things about giving to LeTourneau: today’s investment can become tomorrow’s campus landmark, student experience, or opportunity. There's more to come.
https://www.letu.edu/development/build/index.html

Then and now, we’re still Building with Purpose.

Concrete progress continues at Abbott Aviation.The hangar slab is now poured, elevator walls are underway, and crews are...
09/17/2026

Concrete progress continues at Abbott Aviation.

The hangar slab is now poured, elevator walls are underway, and crews are continuing work on stem walls, piers, and preparation for the classroom slab-on-grade. V***r barrier and wire mesh installation are also moving forward as the next phase takes shape.

Over the next few weeks, work is expected to include classroom and corridor concrete placement, building pad expansion joints, and installation of helical piers for the Outdoor Learning Lab.

We look forward to continued progress!

Thank you to everyone whose generosity is helping keep this project moving forward.

Address

2100 S Mobberly Avenue
Longview, TX
75602

Alerts

Be the first to know and let us send you an email when LeTourneau University Development posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The School

Send a message to LeTourneau University Development:

Shortcuts

Share