10/07/2026
Progress—both above and below ground.
Crews are making significant progress on the Christian Polytechnic University Center (The Burks Center) on foundations and the first areas of slab-on-grade, while underground electrical, plumbing, stormwater, and utility work continues across the site. Column footers are now 75% complete, grade beams are 65% complete, and sanitary and storm sewer rough-ins are nearing completion.
More than 800 cubic yards of concrete have now been placed, and the next few weeks will bring continued foundation work, additional underground infrastructure, and crane mobilization—another sign that the project is preparing to move into its next visible phase.
Every foundation, utility line, and concrete pour is helping prepare a future space designed to serve LeTourneau students for generations.
Thank you to everyone helping us continue to Build with Purpose.