School Construction Pushes on with Scheduled Weekend Work
LeftField, the Towns Owner Project Manager (OPM) has released a notification that Consigli Construction plans to have crews working at Hanaford Elementary School, Frenchtown Elementary School, and East Greenwich High School on Saturday, August 22, 2026, from 7:00 AM to 3:00 PM.
The planned activities for each site are outlined below:
Hanaford Elementary School
Saturday, August 22, 2026 | 7:00 AM – 3:00 PM
• Consigli: Site supervision
• H. Carr: 10 workers continuing framing and sheathing in all zones
• Yardworks: 3–5 workers continuing playground installation
• DiGregorio: Playground area
• Greenwood: Roofing
• Preparations for start of school
East Greenwich High School
Saturday, August 22, 2026 | 7:00 AM – 3:00 PM
• Consigli: Site supervision
• H. Carr: 2–3 workers: Interior addition framing and electrical rough-in
• 2–3 workers: Ongoing Cleaning the Upper Gym and area
• 4–5 workers: Locker room renovations and Wall frames
• Preparations for start of school
Frenchtown Elementary School
Saturday, August 22, 2026 | 7:00 AM – 3:00 PM
• Consigli: Site supervision
• H. Carr: 10 workers framing exterior walls and Sheathing
• DiGregorio: 3 workers performing site work, including excavation for drainage improvements. Prep for SOG
• Preparations for start of school
Work is continuing on schedule with many site improvements to be completed in the coming days in anticipation of the start of school.