High School Addition and Renovation Project Update:
The race to the finish line has been underway all spring and summer with the end in sight! As we prepare to welcome our students back on September 7th, for the start of the new school year, there is still much renovation work to complete in the two short weeks remaining. Contractors have worked through the covid pandemic shutdown and continue despite ongoing issues with labor availability and supply chain hiccups. They all understand that with the goal of having the Main Addition, the 400/500 connector, all classroom renovations, and the Health and Fitness Center completed in time for a move-in in two weeks, there is no time to pause. There are three main projects. The Main Addition, the classroom renovations in both the East and the West buildings, and the Health and Fitness Center.
The Main Addition connects the East and West buildings and includes the new Media Center, the new Cafeteria, the high school main offices, the new Health Suite, the new Counseling Suite, and new classrooms. The Media Center is now occupied by the district as are the high school main offices. In addition, we are currently moving into the new classrooms and the nurses are moving into the new Health Suite.
One of the greatest challenges has resulted in the delays caused by COVID. For example, there were areas of work scheduled for Summer of 2020 but delayed by the impact COVID had on manufacturing and materials, and all these were pushed into the winter and spring. Even though these areas are now complete, the delays did impact renovations scheduled for this summer. That being said, we are still anticipating opening school to our students on Tuesday, September 7th. The status of these renovations will be evaluated on Monday August 30th and if any delays are necessary, that will be determined that week.
Classroom Renovations:
As the construction progressed during the spring of 2021, it was both frustrating and exciting to see the progress being made in the main connector between the East and West Building. We all wanted to have our students passing through the connector from East to West before the year ended. Unfortunately, with all the material delays resulting from COVID, this timeline was never realized.
As the 2020-2021 school year came to a close, the main connector between the East and West buildings was nearing completion. Although we did not have the opportunity to have our students use the main connector in the spring, we moved the principal and the assistant principals along with their support staff into their offices.
The projects scheduled for the summer of 2021 are reflected in the diagram on the right. What was clear is that there was no time to rest and reflect on the progress. The summer push would focus on having instructional areas scheduled for renovations this summer to be ready for our students when they return to full days of instruction in September. With the announcement that there will be no remote instruction option in the fall, the stage was set for a return to in person instruction.
Health and Training Center
The Health and Training Center Project is complete. There are a few supply items that have arrived late due to supply chain issues. This facility includes state-of-the art physical therapy equipment for our trainers to use when helping our student athletes. Soon the new athletic equipment will be installed for all to use. The student athletes and coaches are looking forward to training in this new facility. This equipment will be used by our physical education classes as well as the athletes throughout the school year and throughout the summer months.
August 2021 Status
Throughout the summer, weekly meetings with the Architects, Project Managers, and NB administration have been held to monitor the progress of the projects. Each week our professionals report with confidence that the building will be ready for students in September. It is understood that come September, there will still be work to be completed but the High School should be ‘substantially complete’ and approved for occupancy on September 1st.
At this time, the Main addition connecting the East and West buildings is complete and in the “punch list” phase. The principal and assistant principals have moved into the main office area, counselors moved in last week, and the Cafeteria, Media Center, School Store and Business Classrooms are all ready for school opening. Site work in the front will be complete before Labor Day.
The picture on the right shows the start of the demolition of the agriculture classroom and the old greenhouse. This project began in July. This will make room for the final construction of the bus parking lot and the bus student drop off and pick up area.
The new agriculture classroom is located in the East building adjacent to the new greenhouse which should be ready for school opening in September.
The 400/500 Connector addition is complete. It houses the new Early Childhood Development classroom and the Choral Rooms. These new classrooms connect the 400 wing to the 500 wing and allow students easy passage to the main addition and the East building.
The partial re-roofing project is substantially complete. This contract remains open as this roofing contractor must support installation of rooftop curbs for HVAC equipment included in the 400/500 Connector Project renovations.
Extensive renovations that are included in this Project are being completed. This work includes new Science Labs and the conversion of the old Media Center into four classrooms, and the Board Offices. Other projects nearing completion include new student restrooms, the new Floral Arts Rooms, and the HVAC upgrades throughout.
Please take a moment to review the Project Manager’s PowerPoint presentation located on NB's Construction web page. Simply go to www.nburlington.com and search "High School Construction." Also, photos of the entire project are being organized and uploaded to the Photo Gallery & Video Library section of the web page as well.
The Board of Education would like to once again thank the community for the continued support and patience of all. The combination of construction and COVID has presented a myriad of challenges. Thanks to your support, this much needed construction project will serve our NB students for generations to come.