Please see this update from the North Buckhead Civic Association regarding the Wieuca–Phipps Roundabout. As you plan your travel to Wieuca over the next few weeks, we encourage you to allow extra time and stay aware of changing traffic patterns. We will continue to share updates as they become available.
Roundabout Construction Timeline
The Buckhead Community Improvement District (BCID) is managing this project and has shared the following updates:
• Final milling and paving began around March 23 and will take 2–3 weeks
• Temporary striping will be installed following paving (estimated April 13)
• The roundabout will then shift to dual-lane operation, with guidance provided
• Final thermoplastic striping is expected approximately May 4
Additionally, a new traffic signal at Wieuca and Old Ivy will become operational in the coming weeks. This light is intended to improve left turns and help create safer gaps in traffic for surrounding neighborhoods.