08/11/2021
‘Twas the night before the first day of school! Thanks to the community for being so patient with us during the summer renovation. Thanks to Allen ISD and the amazing staff at Boon for bringing this one home. From everyone at Balfour Beatty, thank you so much for entrusting us with completing this beautiful building!! Have a great year students and teachers!
Sincerely,
Your Balfour Beatty Boys!!
08/08/2021
So excited to get the teachers and staff in yesterday to prep for the first day of school! Pardon our dust while we put the final touches on your beautiful campus.
08/04/2021
Anyone else still awake with the excitement of school starting? We are still here getting everything ready for a great school year!
07/21/2021
Happy Wednesday! The count down is on and we are busy at work putting all the finishes together. The air is on so we are installing ceiling tile, carpet, lights, ceramic tile, cabinets and much more. Playground equipment will start next week with landscaping to follow.
07/13/2021
Happy Tuesday! We have been busy at work putting this beautiful building back together. Please enjoy the photos from today’s walk including the new admin area, gym, playground area, new railings at stairs, a typical classroom and much more. Hope everyone is having a great summer!
05/24/2021
Happy Monday! We made great progress with demo over the weekend. Please see pictures of the admin area taken from the reception desk, cafeteria from stage and library. Have a great week!
05/21/2021
Congratulations on a great year Boon! Last day of school means first day of demo. Please excuse the mess as we improve your beautiful school! Thanks to Ms. Lauren, her staff and everyone at Allen ISD for all the countless hours of prep to make the transition so smooth.
04/20/2021
Happy Tuesday! As scheduled, we have commenced geothermal drilling for the new HVAC system at Boon ES. Drilling will continue until approximately the end of May.
04/19/2021
Happy Monday! Progress is being made in anticipation of geothermal wells starting. The playground area has been removed to allow for new geothermal wells. The wells are just one of many items being added at Boon ES to help improve the overall energy efficiency of the building.
04/12/2021
Temporary Fencing has been installed in preparation for geothermal drilling. The job trailer has also been delivered.