GD4000-L Horizontal Directional Drilling Machine (HDD Rig):
- Max. torque: 110000 N.m
- Max. pulling force: 4000 KN (around 400 tons),
- Max. wrench force: 367000 N.m
- Dimension (L*W*H): 18.6m*3.4m*3.6m
- Rig weight: 56000 kg;
- Max. drill pipe length: 9.6m
- Referential back-reaming diameter: 2000mm; max. length around 2500m.
- Manufacturing date: December 2012, and start using time: June 2013.
** Planned selling price:* Absolute market lowest price, not exceeding 15% of the new machine, sincere purchase can be negotiated.
Although this drilling rig is twelve years old, its actual working time is only six years. Therefore, if your team has good maintenance technicians, you can use this machine very well.
tel.: 0946829236
28/05/2024
October 2023 to May 2024, 6.2 kilometers, granite rock HDD Crossing at Chainet Thailand, so many difficulties, we guys figured out the solutions and successfully completed, good guys, fighting...
28/05/2024
PTT Project, 36" gas pipe, Jacking Crossing, 100m/ 200m/320m bored crossing completed, hard work, fighting...
26/03/2023
Pipeline Crossing Engineering (Thailand) Co., Ltd. together with the Graduate School Faculty of Law and Faculty of Business Administration and Public Administration Organized the 7th charity project for poor children at Ban Morkha Child Development Center, Nong Lu Subdistrict, Sangkhla Buri District, Kanchanaburi Province on April 1, 2023.
06/03/2023
PCE perform in HKPPL Project HDD11 #.Mainline 24"+FOC 4" Length is 800m.
05/03/2023
PCE joined school charity event organized by FPT(Fuel Pipeline Transportation Limited) and TTEC(Triton Engineering and Construction Public Company Limited) to take corporate responsibility for society in Thailand.