25/05/2019

This is the latest aerial video recording taken last May 15 featuring the ongoing construction at the PSHS Main Campus. The video shows three floors (with roof) of the Admin Building and four floors of the SHB Front Extention. The front facade featuring the iconic fins is almost completed.

The unfinished part of the Admin Building is the portion that used to be the school Power House and was the last to be demolished.

The new Academic Building (formerly Cafeteria) shows fifth floor slabs and beam forms of the new building (including residential quarters at the back of the second floor). Slab on grade is completed in the ground floor; CHB laying is being conducted in the second floor.

As of May 7, the Admin Building and SHB Front Extension is at 72.25% completed while the Academic Building is 31.82% completed.

04/01/2019

This is the latest aerial video recording highlighting the ongoing construction at the PSHS Main Campus. The video shows three floors of the Admin Building and four floors of the SHB Front Extention (formerly front lobby). The site of the new Academic Building (formerly Cafeteria) shows three floors of the new building (including residential quarters at the back of the second floor).

As of December 17, 2018, the Admin Building and SHB Front Extension is at 52.72% completed while the Academic Building is 23.84% completed.

12/11/2018

This is the latest aerial video recording highlighting the ongoing construction at the PSHS Main Campus. The video shows two floors of the Admin Building and three floors of the SHB Front Extention (formerly front lobby). The site of the new Academic Building (formerly Cafeteria) shows two floors of the new building (including the stairwell and elevator shafts) and some ongoing excavation.

As of October 30, 2018, the Admin Building and SHB Front Extension is at 42.04 % completed while the Academic Building is 20.15% completed.

12/10/2018

WATER INTERRUPTION - October 12

The Academic Building construction site reported a water leak today; thus, the school main water line is closed temporarily while the contractors are fixing the leak.

Please bear with the inconvenience.

05/10/2018

The aerial video was recorded showing the accomplished first floor of the Admin Building and SHB Front Extention (formerly front lobby). The site of the new Academic Building (formerly Cafeteria) shows ongoing excavation and parts of the foundation for the new building.

05/10/2018

The aerial video was recorded showing the foundation of the Admin Building and Front Lobby. The excavation for the foundation of the Cafeteria is also shown.

04/10/2018

Thanks for the likes! Uploading aerial videos of Pisay Main Campus.

School

Summer is here!
14/04/2018

Summer is here!

Aranan Creek converted to Box Culvert and Soon-to-be Developed as Tambayan for the PSHS-MC Community
21/02/2018

Aranan Creek converted to Box Culvert and Soon-to-be Developed as Tambayan for the PSHS-MC Community