25/05/2019
This is the latest aerial video recording taken last May 15 featuring the ongoing construction at the PSHS Main Campus. The video shows three floors (with roof) of the Admin Building and four floors of the SHB Front Extention. The front facade featuring the iconic fins is almost completed.
The unfinished part of the Admin Building is the portion that used to be the school Power House and was the last to be demolished.
The new Academic Building (formerly Cafeteria) shows fifth floor slabs and beam forms of the new building (including residential quarters at the back of the second floor). Slab on grade is completed in the ground floor; CHB laying is being conducted in the second floor.
As of May 7, the Admin Building and SHB Front Extension is at 72.25% completed while the Academic Building is 31.82% completed.