20/06/2024
20/6/2024 KHAMIS
8️⃣0️⃣0️⃣AM
Meneruskan Kerja Kerja Yang Di JADUALKAN Dan KERJA KERJA TAMBAHAN DAN ASAL
(Di Awalkan)
*Epoxy Primer UNTUK SHS Block 1, Block 2 ,
Block 3
✅ 100%
1)Kerja Kerja Internal Water Piping-Bilik Bilik Air Serta Tempat Wudhu Block 2 Surau
✅ 100%
Dari Main ✅
2)Menyambung Kerja Kerja Perimeter Drain+Sump
-Batu Bata Side Wall Dan Plastering
*Sekeliling
Block 2 ✅ 100%(14/6)
Block 1 ✅ 100%(19/6)
&
Block 3 ✅ 60% (19/6)
3)Kerja Kerja Saliran Longkang Keluar Air
*Dari Block 1 Ke Earth Drain Hadapan
(Setting Out) ✅
(Excavation) On Going ✅ 60%
*Dari Block 3 Ke Earth Drain Belakang
(Setting Out) ✅
(Excavation)On Going
*Quarters 4-2-1 On Going
✅ 80%
4)Kerja Kerja Intermediate BEAM
Block 2
(Di Awalkan)
(Awal July Akan Mula Kerja Kerja Structural Slab Launching)
5) KERJA KERJA RUBBLE WALL(BATU GUNUNG)Kawasan Parking ke Atas Tepi Block 1
--------------------------------------
SCHEDULE OF MATERIALS DELIVERY
(19-30/6/2024)
--------------------------------------
1)Cement X 40 bags
(Kerja Kerja Longkang)
✅ 10/6
2)Cement X 40 bags (2)
(Kerja Kerja Longkang)
✅ 14/6
3)Cement X 40 bags
(Kerja Kerja Longkang
Q1-Q4 PEWAKAF)
✅ 19/6
2)CONCRETE PRECAST 'V' DRAIN
1 40 pcs ✅
2 100 pcs ✅
2)CONCRETE PRECAST
'V' DRAIN COVER
3)UPVC DRAIN PIPE 6"
#100 pcs - to be delivered
4)Pipe Fittings Untuk Bilik Bilik Air Dan Tempat Wudhu Block 2
✅
5)
5.1)**SHS 4x4-
Block 1&Block 3
(1st Floor Beam &
Intermediate Beam)
5.2)**SHS 2x4-
Block 1&Block 3
(1st Floor Beam &
Intermediate Beam)
# # 24-30/6/2024
5.3)**SHS 2x4
4x4
Block 2
(Intermediate Beam)
✅ 19/6
6)Aluminium OUTER Frame
-GF Block 1
-GF Block 3
# #24-30/6
7)Pasir Kasar 2 Load
(Kerja Kerja Longkang
Q3,2,4)
✅ 1 Load(19/6)
8)6x9 Rock-Rubble Wall
X 1 Load
(Di Bawah PEWAKAF Landscape)
Sumbangan tuan/puan di sini:
0501 2010 0974 46 ( BIMB )
Maahad Tahfiz Addirasah
Gambar menyolit
Terima kasih Mr Yau menyampaikan sumbangan buah²an dan pakaian terpakai untuk diedaekan kepada faqir miskin