Update Date 24-25 July 2019: Casting of the Second floor slab of the lecture rooms EAST BLOCK . We are thankful to God who showered upon his blessings in the form of light drizzle after a long period of break this monsoon.The casting started with a small prayer to God ,and request for blessings from all faiths. The safety of the worker's was ensured,by keeping a check on their harnesses and even remind the ones who were negligent/carefree about it, as now we are at a height which is more than 5-6 metres.We would request you all to visit the construction area and give your valuable inputs and blessings/ best wishes for the well being of the school.
We are on schedule as per the proposed plan of action/implementation.