Compensation Delay Raises Concern Among Land-Affected Villagers Under Taliha–Tato Frontier Highway Project:
Nungnu Jurisdiction, Upper Subansiri, Arunachal Pradesh
NUNGNU 19.09.2026 : The prolonged delay in compensation payments for land affected by the Taliha–Tato Frontier Highway Project has become a growing concern among villagers under Nungnu jurisdiction, with 47 beneficiaries reportedly still awaiting their compensation.
According to details from the affected area, a total of 132 land-affected beneficiaries are involved in the compensation process. Of these, 85 beneficiaries have received their payments, while 47 beneficiaries are yet to receive their compensation.
The last compensation payment was reportedly made on 26 June 2025. Since then, the remaining beneficiaries have reportedly continued to wait for their payments, with the pending cases now extending for more than one year.
The prolonged delay has created difficulties for affected families whose land and properties have been impacted by the highway project. For these families, compensation is an important entitlement to help manage the consequences of land acquisition, livelihood disruption and other expenses arising from the project.
Potential Impact on Project Progress:
The unresolved compensation issue may also have implications for the smooth implementation of the highway project. If compensation-related cases continue without timely resolution, they could potentially create difficulties in carrying out work along affected stretches and may impact project progress.
However, the extent to which the pending compensation cases may affect construction will depend on the specific status of land acquisition, possession and project work in the affected areas.
Villagers Seek Early Resolution:
Affected villagers are seeking timely intervention from the concerned authorities to examine the pending cases, clarify the reasons for the delay and ensure that eligible beneficiaries receive their compensation through due process.
They are also seeking greater transparency regarding the 47 pending cases, along with a clear timeline for their resolution.
The Taliha–Tato Frontier Highway is an important infrastructure project for the region, but its implementation also involves the rights and livelihoods of communities whose land is affected.
Timely resolution of the pending compensation cases could help address the concerns of affected families and reduce the possibility of further difficulties during project implementation.
Current Status
•Total land-affected beneficiaries: 132
•Compensation paid: 85
•Compensation pending: 47
•Last payment made: 26 June 2025
•Reported waiting period for pending beneficiaries: More than 1 year