19/06/2026
We have received the following notification for roadworks in our area which may affect you:
Suffolk Highways are planning to carry out improvement works in your area.
What will we be doing?
Phase 1 – Surface dressing preparation
Phase 2 – Surface dressing
Phase 3 – Reinstatement of road markings
Where will we be doing it?
B1066 The Street, Boxted – Part of from Tittle Lane, Boxted to Melford Road Hartest
B1066 Melford Road Hartest – full length
B1066 The Row, Hartest – full length
What are the times and dates of the works?
Phase 1 – Wednesday 17 June, from 9:30am to 2:30pm
Phase 2 – Friday 26 June to Monday 29 June, 10am to 2pm
Phase 3 – Thursday 16 July to Monday 20 July, 8pm to 5am
What traffic management will be in place? While we are working, a road closure will be in place for the safety of highway users and our operatives.
Surface dressing is a very quick process but is also weather dependent. We have scheduled a time window to give us the best chance of completing the work successfully. Please note that the road closure is unlikely to last for the entire duration stated above.
What is the diversion route? B1066, A143, A1302, A134, A1092, B1066 and vice versa.