একজন প্রকৌশলী হিসেবে অবশ্যই আপনার ধারনা থাকতে হবে একটি বিল্ডিংয়ের মোট ১০০% কাজ কিভাবে হিসেব করা হয়ে থাকে। আসুন খুব সহজে মনে রাখি একটি বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়।
তার সম্ভাব্য নমুনা।
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME (Lift, Generator, Substation) = 10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
STRUCTURE 35%
- Footing & Column Padestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8) = 40%
- Roof top = 7%
TOTAL = 100% (৩৫% যেভাবে আসবে।)
BRICK WORK 6%
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (৬% যেভাবে হবে।)
WOOD WORK 5%
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100% (৫% যেভাবে হবে।)
METAL WORK 2%
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100% (২% যেভাবে হবে।)
PLAMBING & SANITARY 6%
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
ELECTRICAL - 7%
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100% (৭% যেভাবে হবে।)
PLASTER 4%
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100% (৪% যেভাবে হবে।)
GENERAL FLOOR TILES 6%
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
TOILET & KIT WALL TILES = 3%
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100% (৩% যেভাবে হবে।)
ALUMINIUM WORK 4%
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Comnon area = 5%
TOTAL = 100% (৪% যেভাবে হবে।)
EME 10%
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100% (১০% যেভাবে হবে।)
PAINT WORK = 3%
- Upto putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tites = 25%
TOTAL = 100% (৩% যেভাবে হবে।)
OTHERS CIVIL WORK = 6%
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100% (৬% যেভাবে হবে।)
UTILITY CONNECTION & BILL = 3%
- DESA/DESCO = 35%
- TITAS = 20
- WASA
Unique Training Center
Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from Unique Training Center, Barisal.
UNIQUE TRAINING CENTER (UTC)
Professional Computer Training Center
Our Course List:
# Auto Cad 2D,3D.
#3Ds Max ,V-ray.
#Microsoft Office, Word ,Excel.
#Web Design & Development.
25/11/2021
প্রফেশনাল অটোক্যাড কোর্স করুন
কোর্স শেষে সার্টিফিকেট প্রদান করা হয়
Cell: 01721894203
21/09/2021
Unique Training Center (UTC)
Professional Computer Training Center
Now we are training:
AUTO CAD 2D, 3D, 3DS MAX, V-RAY, Microsoft Word, Excel .
contract: 01721894203,043161640
Email: [email protected]
21/09/2021
Contact Inbox if you want to learn professional AutoCAD 2D,3D,V-Ray to develop civil engineering skills
Click here to claim your Sponsored Listing.
Location
Contact the school
Website
Address
Barisal
8200