01/06/2026
Construction activities for the Ebeye Seawall PREP II Footpath Project continue to progress steadily along the ocean-side. Current efforts include site grading and surface preparation to enhance pedestrian access and establish a continuous pathway alignment along the seawall. Additionally, cast-in-place reinforced concrete sidewalk sections are in progress. Each concrete panel is constructed with embedded dowels to ensure a robust structural connection between adjacent spans, thereby improving load transfer and the overall performance of the footpath.
Funding for footpath is provided by KADA (compact fund), with an allocation of $2,450,000.00, to cover the shortfall of the WB PREP II project. We sincerely appreciate the support of the people and the Government of the United for addressing this shortfall.
29/05/2026
The Water Catchment Concrete Pad at Mid Corridor Housing Project Stage 1 has been upgraded to improve water management. Originally, the water system for all 12 units was designed to share a single water source and pump, which posed limitations on water distribution and efficiency. To address this, we have implemented a solution where each unit now has its own dedicated water pump and catchment system, ensuring independent water supply and enhanced reliability for residents.
27/05/2026
Update Drainage Works at North Camp Road A: Ongoing trenching activities are underway in preparation for the installation of new drainage pipes along the road leading to the New Beginning Church. A road closure is currently in effect for the duration of this operation. Proper safety signs have been installed to inform the public and ensure safety during the construction period.
25/05/2026
Update on the Drainage Installation Works at North Camp Road C. Backfilling and clearing of the site are currently ongoing to prepare for the next phase. The installation of drainage pipes, as well as the construction of catch basins and manholes along the internal road, has been completed. Temporary catch basin gratings have been installed to ensure the safety of the community in the area, preventing debris from entering the drainage system and reducing the risk of accidents.
22/05/2026
Our contractor working at the Ebeye Mortuary made an incredible find—an etching on the wall bearing the date August 11, 1934. If authentic, this suggests the structure was built during the Japanese era, which is truly remarkable. Does anyone have insights to confirm if this is factual?
20/05/2026
Enebouj Community Center Project Update. Construction activities at the Enebouj Community Center Project continue to progress steadily, with significant advancement made on the reinforced concrete column works, including the installation of vertical rebar cages and formwork. Concrete pouring operations for the remaining columns—each measuring approximately 12 meters in height and 0.8 meters in diameter—were successfully completed today as scheduled, establishing the primary structural framework of the upcoming facility. These columns are designed to support the main roof structure and ensure the building's seismic resilience.
19/05/2026
A joint inspection was conducted today at the Ebeye Morgue Building site, involving teams from the National Telecommunications Authority (NTA) and the KADA (Kwajalein Atoll Development Authority). During the inspection, NTA confirmed the potential relocation of their pedestal cable, which is currently blocking the designated passageway. This adjustment is needed to support the upcoming construction and ensure clear access around the new Morgue Building. The fire hydrant will also be relocated.
19/05/2026
Just giving a quick update on the footpath work at our Ebeye Seawall PREP II Project.